Cpm
A) assumes we do not know ahead of time what activities must be completed.
B) assumes that activity time estimates follow the normal probability distribution.
C) is a deterministic network technique that allows for project crashing.
D) is a network technique that allows three time estimates for each activity in a project.
E) None of the above
C
You might also like to view...
Which of the following is a benefit of efficient supply chain management?
A. Increase in product availability B. Increase in organizational turnover C. Increase in turnaround time D. Decrease in inventory turnover E. Decrease in cross selling
Between the early 1900s and 1930, employers advocated open shops in which all workers, regardless of race, gender, or union status, would be given an equal opportunity to work for them.
Answer the following statement true (T) or false (F)
Unemployment is lower in Japan than in France
Indicate whether the statement is true or false.
________ create specialist sub-units with unique processes, structures and cultures that are specifically intended to support early-stage innovation, comprising one or more innovation teams within the larger parent organization.
a. Ambidextrous organizations b. Strategic business units c. Corporations d. Heterarchical organizations