In PicBasic, to what value would the following expression evaluate:1 + 2 * (3 / 4)
A. 0
B. 2.5
C. 1
D. 1.5
E. 2
Answer: C
You might also like to view...
What converts some measurement of vehicle operation into an electrical signal?
What will be an ideal response?
How do you establish proper drainage in a lawn?
What will be an ideal response?
Revcon Products has two subcontractor bids to automate a composite winding process. Process A will have fixed costs of $42,000 per year and will require two workers at $80 per day each. Together, these workers can generate 100 units. Process B will have fixed costs of $56,000 per year, but with this process, three workers will generate 200 units of product. If x is the number of units, the variable cost (VC) per year for B is best represented as: (choose one)
(a) VC per Year = [2(80)/100]x (b) VC per Year = [3(80)/200]x (c) VC per Year = [3(80)/200]x + 56,000 (d ) VC per Year = [2(80)/100]x + 42,000
Electrical circuit schedules can be used to provide electrical panel, circuits, poles, and amperage requirements and specifications. An electrical panel schedule can be used to provide panel size and type, main circuit size and type, panel manufacturer and model, and wiring specifications.
Answer the following statement true (T) or false (F)