If the resident project representative is verifying the contractor's estimate of work done to date, which of the following is true?
A. Material delivered but not incorporated into the work should be verified and may be included.
B. Material delivered but not used will not be paid for.
C. Unincorporated material will be paid for only if the contractor submits paid receipts to show that it has paid the suppliers.
D. All of the above
E. None of these statements are true.
A
You might also like to view...
Freestanding walls without masonry are typically built of ________.
a. paving brick b. ashlar stone c. rubble d. concrete
List the advantages of using preformed parts.
What will be an ideal response?
Soil organic matter consists of:
A) living organisms and cells. B) dead tissues and wastes. C) identifiable biomolecules. D) polymerized, non-identifiable molecules. E) all of the above
A mason earns $625.00 during week 1, $590.00 during week 2, $605.00 during week 3, $580.00 during week 4 and $585.00 during week 5. What is her average pay for the five weeks?
What will be an ideal response?