Canning Transport is to move goods from three factories to three distribution centers. Information about the move is given below. Give the network model and the linear programming model for this problem.
Shipping cost are:
Min 3XAX + 2XAY + 5XAZ + 9XBX + 10XBY + 5XCX + 6XCY + 4XCZ
s.t. XAX + XAY + XAZ ? 200
XBX + XBY ? 100
XCX + XCY + XCZ ? 150
XDX + XDY + XDZ ? 50
XAX + XBX + XCX + XDX = 250
X AY + XBY + XCY + XDY = 125
XAZ + XBZ + XCZ + XDZ = 125
Xij ? 0
You might also like to view...
Scheduling for line processes is often referred to as ______.
A. cluster scheduling B. flow-shop scheduling C. batch scheduling D. job-shop scheduling
Criticism is a key element of team building. _________________________
Answer the following statement true (T) or false (F)
Many experts recognize that advertising has a lagged or carryover effect; monies spent on advertising do not necessarily have an immediate impact on sales.
Answer the following statement true (T) or false (F)
Agents can collect payoffs made during the course of conducting the principal's business
Indicate whether the statement is true or false