What effect could an extreme shortage of skilled workers have on the cost of a project?
What will be an ideal response?
A shortage of skilled workers may increase the cost of construction. The contractor may have to offer incentives to attract the needed crafts or lesser-trained personnel may have to be used. Either of these scenarios adds to increased construction costs. The incentives increase the unit labor cost while using less trained personnel elongate the amount of time required to complete the task, increasing the labor costs.