A project consisting of six activities is shown in the table. The project manager must achieve the lowest possible maximum resource requirement while adhering to a 34-day deadline
The lowest possible peak resource demand occurs: Activity Duration (days) Activity Cost Predecessor K 10 140 L 8 64 K, M M 12 96 N 6 120 M P 14 168 L Q 12 144 N A) On days 19 through 20 for an early start schedule. B) On days 17 through 20 for a late start schedule. C) On days 13 through 18 for an early start schedule. D) On days 21 through 22 for a late start schedule.
The origin or beginning node in a network is called