Suppose you have the following project digraph. (The numbers in parentheses represent hours.)
Consider the following timeline using two processors.
A. This is the timeline one gets using the decreasing-time algorithm.
B. This timeline is an optimal schedule.
C. This timeline is an illegal schedule.
D. This is the timeline one gets using the critical-path algorithm.
E. none of these
Answer: C