Given an equal level of risk and the need to reduce overall project duration, why would you NOT select the activity with the least slope, in the entire project network, to crash first?
Fill in the blank(s) with the appropriate word(s).
Answer will vary
If it is not on the critical path crashing it will not reduce project duration.
You might also like to view...
Which of the following perspectives argues that there's "one best way" to solve a problem that will work for any organization?
A. The universal perspective B. Behavioral organization theory C. The systems perspective D. The interactional perspective E. The contingency perspective
Opulent Inc., a furniture design company based in Winona, designs a wide range of office and household furniture. Umber Corp. has recently started offering custom-made furniture in the same city. The managers at Opulent are conducting a research to find out the strengths and weaknesses of Umber. The managers are also trying to figure out the strategies used by Umber. Which of the following is a component of the specific environment that is illustrated in the scenario?
A. Competitive analysis B. Deskilling C. Divesting D. Proactive monitoring
What organization can hear arguments from any signatory nation about tariff violations or nontariff barriers?
a. CISG b. WTO c. GATT d. WIPO
An example of a selectively rewarding tax system is
A) high marginal tax rates. B) no tax on the sale of a personal residence. C) taxing personal income, but not wealth. D) a graduated sales tax rate.