Which of the following identifies the project activities that must be completed, the expected start and end dates, and what resources are assigned to each task?

a. Project schedule
b. Project milestone
c. Project deadline
d. Slack time


a. Project schedule
A project schedule identifies the project activities that must be completed, the expected start and end dates, and what resources are assigned to each task. A project schedule is needed to complete a project by a defined deadline, avoid rework, and ensure that people know what to do and when to do it.

Computer Science & Information Technology

You might also like to view...

_____ shows the text of a document without showing its layout.?

A. ?Normal view B. ?Print Previewview C. ?Outlineview D. ?Draftview

Computer Science & Information Technology

A function's ________ defines the rules by which the function operates

Fill in the blank(s) with correct word

Computer Science & Information Technology

Answer the following statement(s) true (T) or false (F)

1. You can modify both HTML and CSS properties in the Page Properties dialog box. 2. A simple error in syntax when writing HTML can keep elements on your page from appearing correctly. 3. The head element of a web page contains content that is displayed to the user at the top of the page. 4. Web pages designed using tables will load faster than those using CSS layout and external style sheets.

Computer Science & Information Technology

What is an accumulator?

What will be an ideal response?

Computer Science & Information Technology