Which of the following identifies the project activities that must be completed, the expected start and end dates, and what resources are assigned to each task?
a. Project schedule
b. Project milestone
c. Project deadline
d. Slack time
a. Project schedule
A project schedule identifies the project activities that must be completed, the expected start and end dates, and what resources are assigned to each task. A project schedule is needed to complete a project by a defined deadline, avoid rework, and ensure that people know what to do and when to do it.
You might also like to view...
_____ shows the text of a document without showing its layout.?
A. ?Normal view B. ?Print Previewview C. ?Outlineview D. ?Draftview
A function's ________ defines the rules by which the function operates
Fill in the blank(s) with correct word
Answer the following statement(s) true (T) or false (F)
1. You can modify both HTML and CSS properties in the Page Properties dialog box. 2. A simple error in syntax when writing HTML can keep elements on your page from appearing correctly. 3. The head element of a web page contains content that is displayed to the user at the top of the page. 4. Web pages designed using tables will load faster than those using CSS layout and external style sheets.
What is an accumulator?
What will be an ideal response?