If the most optimistic time for completing an activity is 3, the most likely time is 4, and the most pessimistic time is 11, then the estimated time for the activity is ______.
A. 5
B. 4
C. 6
D. 9
A. 5
You might also like to view...
Use the following information for Meeker Corp. to determine the amount of equity to report. Cash$ 74,000 Buildings 128,000? Land 212,200? Liabilities 133,000?
A. $414,200. B. $25,200. C. $547,200. D. $281,200. E. $291,200.
Which of the following is not true about goodwill?
a. Goodwill reflects the value of knowledgeable employees. b. Goodwill reflects the value of a reputation for quality products. c. Under U.S. GAAP, goodwill has an indefinite life, and firms do not amortize the amount recognized as goodwill. d. Firms must test goodwill annually for a loss in value. e. Under IFRS, goodwill has an indefinite life, and firms amortize the amount recognized as goodwill.
The support staff is especially influential in a(n) ______ organizational form.
A. adhocracy B. strategic apex C. international strategy D. operating core
The degree to which a person is courteous, likable, good-natured, and flexible” is which of the Big Five dimensions of personality?
b. Extraversion/introversion c. Openness to experience d. Emotional stability