Why is the project duration with the lowest direct costs seldom the optimum duration for a project?
Fill in the blank(s) with the appropriate word(s).
Answer will vary
Indirect costs, those accumulating each day, will at some point outweigh the reduction in direct costs leading to an increase in total costs. The Project Cost-Duration graph is a model that demonstrates this.
You might also like to view...
Which of the following is a total dollar measure of liquidity?
a. accounts receivable turnover ratio b. cash to cash operating cycle c. number of days' sales in inventory d. working capital
One can obtain a clear picture of a company's liquidity by referring to its statement of cash flows
Indicate whether the statement is true or false
The remedies of damages and rescission are available for:
a. material fraudulent misrepresentation. b. negligent misrepresentation. c. innocent misrepresentation d. All of these.
If you are in a networking group of 20 to 40 people, how many possible referrals and leads could you obtain from this group?
a. at least 10 b. at least 15 c. 40 d. an almost incalculable number