The jobs listed below need to be completed. Assume that it is now day 140
If the jobs are sequenced according to the shortest processing time rule, what is the average completion time?
Job Processing Time (days) Job due date (days)
A 20 180
B 30 200
C 10 175
D 16 230
E 18 210
A) 47.6 days
B) 60.2 days
C) 94.0 days
D) 2.5 days
E) 238.0 days
A
You might also like to view...
Writers of periodic reports never mention problems encountered on the job
Indicate whether the statement is true or false
Which of the following devices is used to update microfiche?
A. Record processor B. Processor camera C. Planetary camera D. Rotary camera
A company had $53 missing from petty cash that was not accounted for by petty cash receipts. The correct procedure is to:
A. Debit Petty Cash for $53. B. Debit Cash Over and Short for $53. C. Credit Petty Cash for $53. D. Credit Cash Over and Short for $53. E. Debit Cash for $53.
The replenishment cycle occurs at the
A) customer/retailer interface. B) retailer/distributor interface. C) distributor/manufacturer interface. D) manufacturer/supplier interface.