Under the Endangered Species Act, all federal agencies must

A. avoid the use of all chemicals until the EPA has determined they are safe.
B. prepare an environmental impact statement for actions significantly affecting the environment.
C. avoid damage to habitat critical to the survival of endangered species.
D. All of these are correct.


Answer: C

Business

You might also like to view...

If testing cannot be completed any earlier than four days after the prototype has been built, what type of lag exists?

A. Start to Start B. Start to Finish C. Finish to Finish D. Finish to Start E. Any of these could be correct

Business

Harold says in the presence of three other people that he is giving his automobile to his nephew, and then hands the keys to the car to the nephew. Delivery of the auto has taken place

a. True b. False Indicate whether the statement is true or false

Business

The cash flows for two projects, A and B, are shown in the table, below. Notice that Project A has a life of 3 years and Project B has a 2 year life. Use the replacement chain approach to calculate the NPV of each project over a common life-span

What is the NPV of the Project A chain minus the NPV of the Project B chain? Assume that the cost of capital is 8%. Project CFs Project CFs Time A B 0 -150 -104 1 66 66 2 66 66 3 66 0 NPV $20.09 $13.70 A) $0.45 B) $0.47 C) $0.49 D) $0.50 E) $0.52

Business

Transient client presence tends to be a problem in ________

A) P2P applications B) client/server applications C) both A and B D) neither A nor B

Business