On a project that supports a full-time on site resident project representative and a project manager who is based in the home office, to whom should contractor submittals (including all shop drawings) be submitted first?

A. project manager
B. owner
C. Design Manager
D. resident project representative
E. Depends upon the distance to the project site


D