Suppose you have the following project digraph. (The numbers in parentheses represent hours.)
Using the critical-path algorithm to schedule this project with three processors, the project finishing time is

A. 13 hours.
B. 12 hours.
C. 11 hours.
D. 14 hours.
E. none of these


Answer: D