Define critical path and explain how it is identified once a project schedule is calculated
The Critical Path (CP) is the longest path(s) through the project network; activities on the critical path have zero slack time (ST = 0) and if delayed, will cause the total project to be delayed. Slack time is computed as ST = LS ? ES = LF ? EF.
You might also like to view...
Dizzy is not Edwina's agent but enters into a contract with Frida on Edwina's behalf. Edwina later contacts Frida to approve the contract. This is
A. an agency by agreement. B. an agency by estoppel. C. an agency by ratification. D. not the creation of an agency relationship.
Which of the following does not represent a category of angel investors?
a. micromanagement angels b. entrepreneurial angels c. technology angels d. corporate angels
Airlines such as Emirates exploit the profit pool for competitive advantage by adding fees for a variety of services such as access to airport lounges.
Answer the following statement true (T) or false (F)
Which of the following programs used to be called WebSTAT?
a.SSP b.SPSS c.StatCrunch d.JMP