Suppose you have the following project digraph. (The numbers in parentheses represent hours.)
Using the critical-path algorithm to schedule this project with two processors, the total combined idle time of the two processors is

A. 7 hours.
B. 3 hours.
C. 1 hour.
D. 5 hours.
E. none of these


Answer: B

Mathematics

You might also like to view...

Solve the problem.A swimming pool has the shape of a box with a base that measures 28 m by 13 m and a depth of 3.5 m. How much work is required to pump the water out of the pool when it is full?

A. 21,849,100 J B. 81,934,125 J C. 2,229,500 J D. 43,698,200 J

Mathematics

Divide.(20x8 + 12x4 + 28x2) ÷ 4x2

A. 5x6 + 3x2 + 7 B. 5x8 + 3x4 + 7x2 C. -20x6 + 12x2 - 28 D. 20x6 + 12x2 + 28

Mathematics

Find the cost for the purchase at the last price if the commission is $4 per bond.Bond: PSQLast Price: 62.750Number Purchased: 14

A. $13,944.00 B. $8841.00 C. $8785.00 D. $6275.00

Mathematics

Find the requested value of the variable.x varies inversely as y2. If x = 4 when y = 30, find x when y = 6.

A. x = 80 B. x = 144 C. x = 5 D. x = 100

Mathematics