Which of the following is NOT true regarding period order quantity method (POQ) of lot sizing?

A) POQ and EOQ will try to order the same number of times per year.
B) POQ is better suited to lumpy demand than EOQ.
C) The order quantity is constant.
D) The time interval of inventory coverage is constant.
E) POQ is derived directly from the EOQ.


C

Trades & Technology

You might also like to view...

Chapter 8 has no Review Questions.

What will be an ideal response?

Trades & Technology

Mudsills used to support shores must be sound and _____.

a. rigid b. smooth c. dense d. flexible

Trades & Technology

A resident project representative's principal responsibility on the project is to:

A. assure that the contractor performs per approved plans and specifications. B. advise contractor on how to perform his work. C. issue change order. D. see that contractor performs per codes. E. supervise the construction work.

Trades & Technology

Show that the system in Figure E.8 is linear, time invariant, BIBO unstable and dynamic.

Trades & Technology