Solve the problem.Consider a project consisting of nine tasks (A through I) with the following processing times (in hours):    D(3), E(6), F(4), G(8), H(7), and I(4). If a schedule with three processors has a finishing time of 22 hours, what is the total idle time in the schedule?

A. 16 hours.
B. 14 hours.
C. 12 hours.
D. 10 hours.
E. none of these


Answer: C

Mathematics

You might also like to view...

Use the binomial theorem to expand the expression.(4x + 1)5

A. 1024x5 + 20x4 + 160x3 + 160x2 + 20x + 1 B. 1024x5 + 256x4 + 64x3 + 16x2 + 4x + 1 C. 1024x5 + 1280x4 + 640x3 + 160x2 + 20x + 1 D. (16x2 + 8x + 1)5

Mathematics

Write decimal notation.- 

A. -0.60988 B. -0.060988 C. -6.0988 D. -60.988

Mathematics

Find the area of the figure. Use 3.14 for ?.

A. 20.6934 ft2 B. 41.3868 ft2 C. 43.836 ft2 D. Not enough data

Mathematics

Estimate the sum as indicated. Then answer the question.Estimate the following sum by first rounding to the nearest hundred. Does the estimate give you reason to doubt the stated sum? 

A. Estimate: 12,900 ; yes B. Estimate: 12,900 ; no C. Estimate: 12,600 ; no D. Estimate: 12,600 ; yes

Mathematics