Project risk is calculated by ______.

a. historical experience with projects succeeding or not succeeding
b. the subjective judgment of the project manager
c. multiplying the likelihood of event happening with consequences of event
d. dividing the likelihood of event happening with consequences of event


c. multiplying the likelihood of event happening with consequences of event

Business

You might also like to view...

Which of the following phrases is the best illustration of homogamy?

A) Opposites attract B) Birds of a feather flock together C) Leave no stone unturned D) To the victor go the spoils

Business

You have been hired as a consultant by Feludi Inc.'s CFO, who wants you to help her estimate the cost of capital. You have been provided with the following data: rRF = 4.10%; RPM = 5.25%; and b = 1.30. Based on the CAPM approach, what is the cost of common from reinvested earnings?

A. 9.67% B. 9.97% C. 10.28% D. 10.60% E. 10.93%

Business

Which of the four types of diversity face the most discrimination?

a. age b. gender c. race/ethnicity d. disability

Business

Those corporations whose stock is traded on the national securities exchanges are known as publicly held corporations

Indicate whether the statement is true or false

Business