Compute the expected time for the task.
Following are the three time estimates for a task in a project:
optimistic completion time = 2 weeks
most likely completion time = 4 weeks
pessimistic completion time = 7 weeks
A) 3.5 weeks
B) 4.167 weeks
C) 5.23 weeks
D) 5.75 weeks
B) 4.167 weeks
You might also like to view...
____________________ is a rise in the general level of prices in the economy and results in a decrease in purchasing power
Fill in the blank(s) with correct word
The variation in media availability is a strong reason to use ________ media consultants.
Fill in the blank(s) with the appropriate word(s).
When the NLRB determine which employees are eligible to vote in an election and will be represented by the union if the union wins the election, it is defining a(an) ________.
What will be an ideal response?
If the seller has failed to comply with Code requirements in making a resale of goods that were wrongfully rejected, a good faith purchaser at the resale takes the goods subject to rights of the original buyer
a. True b. False Indicate whether the statement is true or false