Under the Eichleay formula, what three things must the claimant prove in order to use this formula?

What will be an ideal response?


The three things that must be proven are (1) a government-caused delay
extended the contract completion date, (2) the contractor was required to be
on standby for an uncertain period of time, and (3) the contractor was unable
to take on replacement or substitute work during the delay.

Trades & Technology

You might also like to view...

Which of the following is/are not true of agriculture in the 1700s?

a. Virtually all households farmed. b. Extra family food was sold or bartered. c. Poor transportation required communities to be self-sufficient. d. The whole value chain was essentially done on each farm. e. All of the above.

Trades & Technology

Which of the following is not a savings in precision or quality when working with a robot?

A. Higher levels of customer satisfaction B. The ability to replace worn-out motors C. Tighter tolerances on parts produced D. Reduction in scrapped parts

Trades & Technology

The maximum number of problems that should be addressed in the early stages of the quality program is _____.

a. three b. six c. four d. two

Trades & Technology

In a transformer, the coil containing the AC voltage is referred to as the ____________________.

Fill in the blank(s) with the appropriate word(s).

Trades & Technology