Which of these statements regarding project crashing is true?
A) Crashing is not possible unless there are multiple critical paths.
B) Activities not on the critical path cannot become critical after crashing.
C) Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
D) Crashing a project often reduces the time it takes for lengthy or complex, but noncritical activities.
Answer: C
You might also like to view...
Visual and peripheral cues are important in developing effective emotional appeals
Indicate whether the statement is true or false
Smith Corporation has numerous customers. Customer files are kept on disk storage. Each account in the customer file contains name, address, credit limit, and account balance. The auditor wishes to test these files to determine whether credit limits are being exceeded. The best procedure for the auditor to follow would be to:
A. Use generalized audit software to develop test data that would cause some account balance to exceed the credit limit and determine if the system properly detects such situations. B. Use generalized audit software to compare credit limits with account balances and print out the details of any account with a balance exceeding its credit limit. C. Request a printout of a sample of account balances so they can be individually checked against the credit limits. D. Require a printout of all account balances so they can be manually checked against the credit limits.
The speed of the Internet and the pervasiveness of social media and viral communications mean that people and companies are always ________
A) viewed more favorably in a crisis B) one step away from crisis C) less vulnerable to a crisis D) more glamorous after a crisis
Under the "perfect tender rule" the buyer may reject the goods if they fail in any respect to conform to the contract
a. True b. False Indicate whether the statement is true or false