What is a common problem in calculating start and finish times? Provide an example.

What will be an ideal response?


To calculate the finish day or date, you add the duration to the start day or date. When you do this, you must be very careful not to add too many days. For example, if a task starts on Day 10 and has a 5 day duration, then the task would finish on Day 14 – not Day 15.

Computer Science & Information Technology

You might also like to view...

When the ________ button is active, the nonprinting characters in the document are visible on the screen

A) Text B) Mark/Clear C) Highlight D) Show/Hide

Computer Science & Information Technology

What is the second argument of the IF function?

A) lookup_value B) logical_test C) Value_if_true D) Value_if_false

Computer Science & Information Technology

Dialog boxes often contain content not on the Ribbon

Indicate whether the statement is true or false

Computer Science & Information Technology

Event Viewer, Performance Monitor, and Command Prompt are found in which tab of the System Configuration tab?

A. Startup B. Boot C. Services D. Tools

Computer Science & Information Technology