The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. The construction company must pay a penalty if the project is not finished by the due date in the contract
If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, what due date (project week #) should be negotiated?
A) 81.28
B) 92.8
C) 81.82
D) .81954
E) None of the above
B
You might also like to view...
______ is power than is based on the way that authority is distributed among individuals and teams within an organization.
A. Expert power B. Organizational power C. Personal power D. Referent power
A producer of ____ would not use a process costing system
a. gasoline b. potato chips c. blank videotapes d. stained glass windows
Prejudice translates to ______ when action is taken for or more frequently against members of this out-group.
A. interdependence B. discrimination C. biculturalism D. ethnocentrism
Motivation refers to forces that
A. are basically involuntary. B. energize, direct, and sustain a person's efforts. C. promote groupthink. D. reduce group cohesiveness. E. are acquired through education.