A commercial project requires the installation of 127 square yards of carpet. Using a productivity rate of 0.108 labor hours per square yard and a productivity factor of 1.05, determine the number of labor hours required to install the carpet.
What will be an ideal response?
Using Formula 7-2 we get:
Labor hours = 127 syd × 0.108 lhr per syd = 13.72 lhr
Using Formula 7-3, we get:
Adjusted labor hours = 13.72 lhr × 1.05 = 14.4 lhr – Use 15 lhr
You might also like to view...
Positive caster occurs when the caster line through the centers of the lower ball joint and upper strut mount is tilted forward in relation to the true vertical centerline of the tire and wheel viewed from the side.
Answer the following statement true (T) or false (F)
The __________ of swine is becoming more popular and practical, providing producers with access to superior genetics.
Fill in the blank(s) with the appropriate word(s).
In a move that backfired, Gorbachev tried to increase productivity by limiting sales of which commodity?
a. alcohol b. tobacco c. chairs d. chocolate
Soft copper tubing can be joined by:
A) Compression fittings. B) Brazing, soldering, flaring, or compression. C) Soldering and brazing. D) Flare fittings.