A production engineer wanted to know how long it should take to make metal rods with a lathe. Four rods were made, and the time was recorded. The results were 28.5 seconds, 29.2 seconds, 31.8 seconds, and 29.7 seconds. Compute the total time to make all four rods


28.5 + 29.2 + 31.8 + 29.7 = 119.2 seconds

Business

You might also like to view...

A census is defined as an accounting of everyone in the sample

Indicate whether the statement is true or false

Business

In a just-in-time (JIT) environment, design changes may be made at any time during the production process

Indicate whether the statement is true or false

Business

Given the following notation, what is the break-even sales level in units? SP = selling price per unit, FC = total fixed cost, VC = variable cost per unit

a. SP/(FC/VC) b. FC/(VC/SP) c. VC/(SP - FC) d. FC/(SP - VC)

Business

David has decided to open an auto-detailing business. He will pick up an automobile from the client, take it to his parents' garage, detail it, and return it to the client

If he does all of the work himself and takes no legal steps to form a special organization, which type of business organization, in effect, has he chosen? A) A limited-liability company B) A partnership C) A corporation D) A sole proprietorship

Business