Determine the slack for activity D
Consider the following project.
Activity Immediate Processor Activity Time (days)
A - 6
B - 8
C A, B 5
D B 4
E C 7
F C, D 3
G D 6
H E, F, G 5
A) 2 days
B) 4 days
C) 6 days
D) 5 days
Answer: A
You might also like to view...
If P(A) = 0.58, P(B) = 0.44, and P(A?B) = 0.25, then P(A?B) =
A. 1.02. B. 0.77. C. 0.11. D. 0.39.
Kasien costing provides fixed standards which reflect continuous improvement efforts
Indicate whether the statement is true or false
Which of the following occurs during a novation?
A) All parties agree to substitute new parties for the original parties to the agreement. B) One of the parties to the contract names a third party as the beneficiary. C) One of the parties to the contract assigns his contract rights to a third party without obtaining the other parties' consent. D) All parties agree to lower the contract price.