The most common method used in the preparation of a bill of materials is to prepare ____.

A. one bill for each product type used in a job
B. one complete bill of materials covering all of the precast concrete members in a job
C. individual bills of materials for each individual precast concrete member in a job
D. separate bills of materials for each of the separate section drawings in a jobĀ 


Answer: A

Trades & Technology

You might also like to view...

Radon moves up through the soil and flows into the atmosphere at high and usually harmful rates

Indicate whether the statement is true or false.

Trades & Technology

The ____________________ is an assembly of electrical wires, connectors, and fasteners used to

transmit electricity into a building from outdoor lines.

Fill in the blank(s) with the appropriate word(s).

Trades & Technology

When leak testing a low-pressure chiller, the pressure should not be allowed to exceed 10 psig to avoid:

A) High compressor current draw. B) Opening the high-pressure cutout and shutting the system down. C) Freezing the chiller bundle. D) Breaking the rupture disk and losing the refrigerant charge.

Trades & Technology

Describe the common characteristics of several methods of checking material hardness.

What will be an ideal response?

Trades & Technology