A datacenter has exceeded the load on the central uninterruptible power supply (UPS) for the room and is causing power load problems. Additional power is available, but not using the central UPS. Which of the following is the BEST temporary solution for adding new servers until an upgrade of the central UPS can occur?
A. Continue plugging into the central UPS, but put the UPS on bypass to avoid load problems.
B. Plug the servers directly into the power that is not on the UPS.
C. Add stand alone UPSs for new servers not wired off the central UPS.
D. Continue plugging into the central UPS because the actual load supported is actually higher than stated.
Answer: C. Add stand alone UPSs for new servers not wired off the central UPS.
You might also like to view...
methods are also commonly called ________ methods and get methods are also commonly called ________ methods.
a. query, mutator. b. accessor, mutator. c. mutator, accessor. d. query, accessor.
The cleaner and more ________ the image you project on LinkedIn and other social networks, the better your chances for obtaining a job
Fill in the blank(s) with correct word
The ________ option treats all of the text in the text box as a single animation
A) One Object B) All at Once C) By Paragraph D) By Word
Work recovery time (WRT) is the difference between RTO and MTD
Indicate whether the statement is true or false.