F & R Construction, Inc has consistently used the percentage-of-completion method of recognizing revenue. Last year F & R started work on a $5,000,000 construction contract, which was completed this year. The accounting records disclosed the following data for last year: Progress billings ..................................... $1,500,000 Costs incurred

1,350,000 Collections ........................................... 1,050,000 Estimated cost to complete ............................ 2,600,000 How much revenue should F & R have recognized on this contract last year?
a. $1,500,000
b. $1,700,000
c. $1,100,000
d. $400,000


B

Business

You might also like to view...

"List four steps required for safe lifting" is an example of a(n)

A) central idea B) introduction C) thesis D) speci?c purpose

Business

During which stage of team development should the team leader help clarify team norms and values?

A. Adjourning B. Storming C. Forming D. Performing E. Norming

Business

The functions performed by the mailroom should not be used to determine the layout of the mailroom

Indicate whether the statement is true or false.

Business

Which are horizontal lines in the U.S. Government Survey?

A) Parallels B) Baselines C) Prime meridians D) Both a and b

Business