Use the information in the table (all times are in days) to determine the lowest extra cost for an 18-day project if the base cost for each activity finished in normal time is $1,000
Activity Normal Time Minimum Time Crash Cost ($/day) Predecessor
A 10 6 $70 --
B 6 3 $40 --
C 2 2 -- B
D 4 2 $60 C
E 6 4 $80 A
F 8 5 $90 D, E
A) $400
B) $420
C) $440
D) $460
D
You might also like to view...
Balance of power is most likely the issue a salesperson must consider when responding to a ________ tactic
A) budget limitation B) feel-felt-found C) let-us-split-the-difference D) "if...then" E) "sell low now, make profits later"
Which of the following is reported for interim financial reports using the discrete approach?
A. Change in accounting principle. B. Discontinued operations. C. Seasonal items. D. Income tax expense. E. Property tax expense.
Discuss the confined re-emergence entrepreneur and his or her opportunities.
What will be an ideal response?
A high-cost product is typically aligned with which of the following?
a. Low levels of customer service b. High levels of quality c. Low levels of quality d. Neither high nor low levels of customer service