Use the earned value table to determine the schedule performance index given the indicated state of the project
Activity 5 10 15 20 25 30 35 Plan % Complete
A 850 350 1,200 100%
B 400 125 525 100%
C 1,275 650 1,925 100%
D 2800 4,500 350 7,650 95%
E 680 400 1,080 75%
F 125 875 1,000 80%
G 300 1200 1,500 45%
Monthly Plan 850 750 1,400 3,450 5,180 1,175 2,075 14,880
Monthly Act 900 650 1,350 3,875 4,780 850 2,000
A) 0.89
B) 0.92
C) 1.09
D) 1.13
A
You might also like to view...
Supplies can be classified as two kinds: heterogeneous supplies and homogeneous supplies
Indicate whether the statement is true or false
The American interpretation of the term "exchange contracts" excludes securities contracts
Indicate whether the statement is true or false
According to the textbook, expressing disrespect
a. can result in getting murdered b. can lead to divorce and break-ups in relationships c. may have contributed to the American and French Revolutions d. all of the above
Choosing suppliers simply based on the lowest bid has become a somewhat rare approach
Indicate whether the statement is true or false