When reaching a decision during the group decision-making process, the project manager must build a consensus among the group and can do this by all of the following EXCEPT
A. If time becomes a factor, they must make an informed final decision after everyone's ideas have been heard.
B. Provide periodic summaries to help the group keep track of its progress.
C. Guarantee that everyone has the opportunity to share opinions.
D. Manage any conflict that may arise.
E. Protect those members who represent the minority view.
Answer: A
You might also like to view...
Answer the following statements true (T) or false (F)
1. Depreciation is the allocation of a plant asset's cost to expense over its useful life. 2. An asset is considered to be obsolete when a newer asset can perform the job more efficiently 3. Depreciation means that the business sets aside cash to replace an asset when it is used up. 4. Residual value is also known as depreciable cost.
The Consumer Product Safety Commission:
A. can file suit in federal court against manufacturers of imminently hazardous consumer products in an effort to eliminate the danger posed by such products. B. provides the consumer with important credit information involving leases of consumer goods for more than four months. C. was established by the Consumer Leasing Act. D. is not entitled to issue product safety standards when the product in question presents an unreasonable risk of injury.
A check that has a full endorsement can be further endorsed by any bearer and, therefore, is not as safe as a check with a blank endorsement.
Answer the following statement true (T) or false (F)
To inhibit identity fraud, law-enforcement officials suggest that you:
A) Unless legally required, never put your social security number on any document. B) Obtain and review copies of your credit report at least twice each year. C) Use passwords other than maiden names and birthdays on bank accounts. D) All of the above.