What is an example of a construction activity that is properly scheduled in terms of working days and calendar days?
What will be an ideal response?
Most activities where labor is involved will generally be best scheduled in
terms of working days. A variety of examples would include framing walls, installing
pipe, running cable, hanging doors, laying brick, decking, etc. Examples of activities that
might be best scheduled in terms of calendar days are those in which the primary
resource being utilized is time itself. One example regularly included here is curing of
concrete, primarily because the concrete will cure whether labor is performed or not.
Dewatering and some procurement activities will also be scheduled in terms of calendar
days.
You might also like to view...
What is the purpose of the zone 1 (master) thermostat in the basic zone control system?
A) The zone 1 thermostat controls the master bedroom. B) The zone 1 thermostat determines the operational mode of the equipment. C) The zone 1 thermostat controls the operation of all zone dampers. D) The zone 1 thermostat determines the on and off cycling of the unit.
In what form is most broiler meat sold in the United States?
A. Whole B. Cut-up parts C. Further Processed D. Fully Cooked
The most basic torque wrench is called the _____ torque wrench
A. deflecting beam B. dial indicating C. micrometer D. combunation
The schematic diagram resembles a ladder in that it is made up of two vertical lines representing the incoming electrical sources.
Answer the following statement true (T) or false (F)