The first step in the creation of a Program Evaluation Review Technique (PERT)/Critical Path Method (CPM) chart is to _____.

A. select the graphical planning aids to use
B. determine the logical order of project tasks
C. determine the status of all tasks
D. identify all the project tasks


Answer: D

Computer Science & Information Technology

You might also like to view...

Which of the following is the method used to display a dialog box to gather input?

a. showMessageDialog. b. getInput. c. inputDialog. d. showInputDialog.

Computer Science & Information Technology

How can you counter VBScript vulnerabilities if you are administering a network?

What will be an ideal response?

Computer Science & Information Technology

Answer the following statement(s) true (T) or false (F)

1. A new work using copyrighted work can be copyrightable in and of itself, but it must differ sufficiently from the original or it must contain a substantial amount of new material. 2. Copyright attaches to a work after 23 years. 3. You do not have to get permission to use copyrighted material as long as you cite the source. 4. Stage 5 in planning a successful project is scheduling.

Computer Science & Information Technology

____ is software that the author allows you to download and use without charge.

A. Freeware B. Shareware C. Streaming media D. Online learning

Computer Science & Information Technology