The first step in the creation of a Program Evaluation Review Technique (PERT)/Critical Path Method (CPM) chart is to _____.
A. select the graphical planning aids to use
B. determine the logical order of project tasks
C. determine the status of all tasks
D. identify all the project tasks
Answer: D
You might also like to view...
Which of the following is the method used to display a dialog box to gather input?
a. showMessageDialog. b. getInput. c. inputDialog. d. showInputDialog.
How can you counter VBScript vulnerabilities if you are administering a network?
What will be an ideal response?
Answer the following statement(s) true (T) or false (F)
1. A new work using copyrighted work can be copyrightable in and of itself, but it must differ sufficiently from the original or it must contain a substantial amount of new material. 2. Copyright attaches to a work after 23 years. 3. You do not have to get permission to use copyrighted material as long as you cite the source. 4. Stage 5 in planning a successful project is scheduling.
____ is software that the author allows you to download and use without charge.
A. Freeware B. Shareware C. Streaming media D. Online learning