Use the information in the table regarding this seven-month project to calculate the SPI in terms of dollars and compare it with the SPI calculated in terms of time. Perform both calculations for months 1 through 6

Then use the SPI(t) to provide the Estimate at Completion for Time (EACt).

Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7
PV ($) $125 $275 $500 $875 $1,485 $2,325 $2,670
EV ($) $150 $320 $510 $850 $1425 $2280 $0


Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7
PV ($) $125 $275 $500 $875 $1,485 $2,325 $2,670
EV ($) $150 $320 $510 $850 $1425 $2280 $0
SV ($) $25 $45 $10 -$25 -$60 -$45
SPI ($) 1.20 1.16 1.02 0.97 0.96 0.98

C 1 2 3 3 4 5
ES 1.2 3.3 4.04 3.93 4.90 5.95
SV(t) 0.20 1.3 1.04 -0.67 -0.09 -0.05
SPI(t) 1.20 1.65 1.35 0.98 0.98 0.99
The Estimate at Completion for Time is:

EACt = = = 7.063 months

Business

You might also like to view...

Internal databases usually can be accessed more quickly and cheaply than other information sources

Indicate whether the statement is true or false

Business

In a consolidated balance sheet, the minority interest is reported

a. as part of long-term liabilities. b. between liabilities and stockholders' equity c. as part of stockholders' equity. d. as part of long-term assets.

Business

Clara ended her business letter's with "Your's truly."

What will be an ideal response?

Business

When production equipment is similar, home office control of quality in foreign affiliates is more difficult because management must ensure that all plants adhere to the same standard.

Answer the following statement true (T) or false (F)

Business