The earliest start time rule
a. compares the starting times of all activities for successors of an activity.
b. compares the finish times for all immediate predecessors of an activity.
c. determines when the project can begin.
d. determines when the project must begin.
b. compares the finish times for all immediate predecessors of an activity.
You might also like to view...
What are the two questions that need to be asked when analyzing the nature of a current relationship?
What will be an ideal response?
______ has now become both an evaluation mechanism of OD effectiveness and an intervention in itself.
a. Organizational engagement b. Change management c. Organizational learning d. Employee engagement
The purpose of OSHA and the MSHA is to eliminate injury in the workplace
a. True b. False
An ad for a tennis camp shows a background photo of tennis balls on which the camp's dates and locations are printed. Which of the following was most likely responsible for the tennis ball photo?
A. the copywriter B. the art director C. the PR representative D. the publicity expert E. the layout artist