A budget that is based on a single estimate of sales volume is called a:

A. sunk cost budget.
B. variable budget.
C. flexible budget.
D. static budget.


Answer: D

Business

You might also like to view...

Which priority in the 1990s and early 2000s negatively affected corporations' commitments to social responsibility?

A) a shift in attention to making as much money as possible B) meeting only demands of the Board of Directors C) being responsible only to diverse, multicultural communities D) recognizing only needs of shareowners

Business

A sampling distribution ______.

a. describes the randomness of the variation in a sample’s values b. shows how much of the entire population varies from the sample c. is similar to a histogram d. shows from which parts of the population a sample is chosen

Business

Determining the best choice for organizational structure relies in part on the characteristics of an organization's human resources.

Answer the following statement true (T) or false (F)

Business

Compute the Work-in-Process transferred to the finished goods warehouse on April 30 using the following information:   Work-In-Process Inventory, April 30$175Direct material purchased during April 150Work-In-Process Inventory, April 1 200Direct labor costs incurred 300Manufacturing overhead costs 250Direct materials used in production 125

A. $700. B. $750. C. $675. D. $650.

Business