If a project has exactly one critical path, which of the following statements is TRUE?
A) Crashing an activity on the critical path will always result in an increase in total project profits.
B) Activities on the critical path cannot be crashed.
C) Crashing an activity on the critical path will always result in a reduced total project completion time.
D) The best schedule is one in which all activities are crashed as much as possible.
C
You might also like to view...
_________ uses physically dispersed experts who fill out questionnaires to generate ideas and the judgments are combined into an expert consensus.
A. Brainstorming B. PM C. TQM D. Brainwriting E. The Delphi technique
The supply-side method identifies the effect sponsorship has on consumers' brand knowledge
Indicate whether the statement is true or false
The supervisor should ask what kind of questions of the employee during the performance evaluation discussion?
a. Tough b. Direct c. Open-ended d. Closed-ended
Sketch a 2 × 2 risk management assessment matrix and discuss the impact of each quadrant
What will be an ideal response?