If a project is scheduled from a Start date and you enter a Start date into the Entry table for a task, then Project 2010 will automatically apply the ____ constraint type to that task.
A. Start No Earlier Than
B. Start No Later Than
C. Finish No Later Than
D. Finish No Earlier Than
Answer: A