Assume there are five jobs (i.e., A, B, C, D, and E) that need to be sequenced in a production schedule. The remaining operating time necessary for completion of job A is 3 days (i.e., job A will take 3 more days to complete), B will take 9 days, C will take 6 days, D will take 5 days and E will take 8 days. Which job should be scheduled last if using the SOT priority rule for job sequencing?
A. A
B. B
C. C
D. D
E. E
Answer: B
You might also like to view...
Pinterest's users are predominantly women.
Answer the following statement true (T) or false (F)
Income under absorption costing will always be different than income under variable costing.
Answer the following statement true (T) or false (F)
Allison Engines Corporation has established a target capital structure of 40 percent debt and 60 percent common equity. The firm expects to earn $150,000 in after-tax income during the coming year, and it will retain 30 percent of those earnings. What is the break point of retained earnings?
A. $175,000 B. $75,000 C. $112,500 D. $500,000 E. $250,000
Property damaged by a hit-and-run driver is covered by uninsured motorist insurance
Indicate whether the statement is true or false