Use the earned value table to determine the cost performance index given the indicated state of the project
Activity 5 10 15 20 25 30 35 Plan % Complete
A 850 350 1,200 100%
B 400 125 525 100%
C 1,275 650 1,925 100%
D 2800 4,500 350 7,650 95%
E 680 400 1,080 75%
F 125 875 1,000 80%
G 300 1200 1,500 45%
Monthly Plan 850 750 1,400 3,450 5,180 1,175 2,075 14,880
Monthly Act 900 650 1,350 3,875 4,780 850 2,000
A) 0.89
B) 0.92
C) 1.09
D) 1.13
B
You might also like to view...
Negligence is an intentional breach of duty that may or may not result in harm to another.
Answer the following statement true (T) or false (F)
Lean's primary goal is to eliminate waste in business processes
Indicate whether the statement is true or false
Which of the following statements about flexible budgeting is true?
a. A flexible budget deals with both fixed and variable overhead. b. If all the activity levels are within the relevant range, costs at each successive level should equal the previous level plus a uniform monetary increment for each variable cost factor. c. the activity levels shown on flexible budgets cover the contemplated range of activities for the upcoming period. d. All of the above statements are true.
In what type of retail situation would the old cliché "location, location, location" be true?
What will be an ideal response?