Which of the following correctly pairs a technique with its approach?

A. The program evaluation and review technique (PERT) uses probabilistic estimation to determine the duration of an activity.
B. The critical path method (CPM) uses subjective estimation to determine the duration of an activity.
C. The program evaluation and review technique (PERT) uses optimistic estimation to determine the duration of an activity.
D. The critical path method (CPM) uses pessimistic estimation to determine the duration of an activity.


A. The program evaluation and review technique (PERT) uses probabilistic estimation to determine the duration of an activity.

Business

You might also like to view...

Intelligence as a leader characteristic is found in which of the following approaches?

A. behavioral and trait B. trait and situational C. skills and behavioral D. skills and trait

Business

In a letter advertising its recycling services, The Greenfield Recycling Company stresses that customers will feel the satisfaction of knowing that they have helped to preserve the environment. This persuasive technique relies on ________

A) direct benefits to the reader B) expert opinion C) facts and statistics D) indirect benefits to the reader

Business

A client is a computer that is designed to support processing from many remote computers and users.

Answer the following statement true (T) or false (F)

Business

A resource loading table is created through identifying the project activities and the resources required for completion and applying this information to the project schedule baseline

Indicate whether the statement is true or false

Business