Which of the following is a step that should be followed in the event of a change control request?
A) An appropriate manager within the business unit signs the request, signifying approval.
B) The IT security unit verifies that this change will not cause any security problems.
C) The date and time for the change is scheduled, and all relevant parties are notified.
D) All of the above
D) All of the above
You might also like to view...
What are the four kinds of prototyping?
What will be an ideal response?
Third-party cookies can be stolen and used to impersonate the user, while first-party cookies can be used to track the browsing or buying habits of a user.
Answer the following statement true (T) or false (F)
When might you not want to skip a tab stop?
A) Combo Box field B) Calculated field C) AutoNumber field D) Any time the field requires no data entry
Which of the following shows in the default setting "Show Only Comments and Formatting in Balloons"?
A) Formatting B) Comments and formatting C) Insertions and deletions D) Comments