The project shown below has crash costs as shown in the table. What is the minimum completion cost for this project that has a fixed cost of $1,000 per day?

Activity Normal Duration (days) Crash Duration (days) Crash Cost ($/day)
A 3 3
B 8 5 $800
C 6 4 $1200
D 9 4 $600
E 6 5 $400
F 6 4 $1100
G 2 1 $900
What will be an ideal response?


Answer: Initially, the path lengths are: ABCG = 19; ADG = 14; and AEFG = 17, so the project costs $19,000.
Reducing B by 2 days costs $1600, saves $400, and yields two critical paths of ABCG =
AEFG = 17.
Reducing G by 1 day costs $900, saves $100, and yields two critical paths of ABCG =
AEFG = 16.
Further reductions are possible, but these are not economical, so the minimum cost project completion time is 16 days and the total cost is 16($1000) + $1600 + $900 = $18,500.

Business

You might also like to view...

Who has the main responsibility of developing a formal discipline process for the workplace?

A. the human resource department B. the sales force C. arbitrators D. outplacement counselors E. the legal department

Business

When a partner sells his interest to another party, the journal entry simply credits the withdrawing partner's capital account and debits the new partner's capital.

A) Admitting a new partner does not change the core structure of the old partnership. B) The purchase of an existing partner's interest is a transaction between the new partner and the partnership firm. C) Any time the partner mix changes, the old partnership ceases to exist and a new partnership begins. D) A person can become a partner by purchasing an existing partner's interest, even without the approval of the other partners.

Business

Absorption costing considers ________ as product costs.

A) variable manufacturing overhead B) sales salaries and commissions C) administrative office salaries D) advertising costs

Business

An example of very large-scale integration would be:

a. vacuum cubes b. transistors c. artificial intelligence d. the average personal computer e. ENIAC

Business