Using the information below, compute cycle time: Process time6.0hoursInspections time0.5hoursMove time0.6hoursWait time0.9hoursStorage time72.0hours

A. 80.0 hours.
B. 7.5 hours.
C. 8.0 hours.
D. 6.5 hours.
E. 7.1 hours.


Answer: C

Business

You might also like to view...

Which of the following would not appear on the selling and administrative budget of O'dell Company?

A) Rent Expense B) Depreciation Expense C) Salaries Expense D) Indirect Labor

Business

The specific purpose is stated as

a. an infinitive phrase. b. a full sentence. c. several full sentences. d. one word.

Business

________ is a point along a chain of events caused by a negligent party after which this party is no longer legally responsible for the consequences of his or her actions.

A. Causation in fact B. The point of reason C. The point of appropriation D. Proximate cause

Business

An appraisal cost is created by

a. installing automated technology. b. reworking products. c. verifying procedures. d. rescheduling and setup.

Business