Using the information below, compute cycle time: Process time6.0hoursInspections time0.5hoursMove time0.6hoursWait time0.9hoursStorage time72.0hours
A. 80.0 hours.
B. 7.5 hours.
C. 8.0 hours.
D. 6.5 hours.
E. 7.1 hours.
Answer: C