Suppose you have the following project digraph. (The numbers in parentheses represent hours.)
Using the critical-path algorithm to schedule this project with three processors results in a finishing time of

A. 24 hours.
B. 22 hours.
C. 21 hours.
D. 20 hours.
E. none of these


Answer: C

Mathematics

You might also like to view...

Solve the problem.The weight of a liquid varies directly as its volume V. If the weight of the liquid in a cubical container 4 cm on a side is 128 g, find the weight of the liquid in a cubical container 3 cm on a side.

A. 27 g B. 54 g C. 6 g D. 15 g

Mathematics

Write the percent as a decimal.0.60%

A. 0.6 B. 0.06 C. 0.007 D. 0.006

Mathematics

Use the maximum/minimum finder on a graphing calculator to determine the approximate location of all local extrema.f(x) = 0.1x5 + 5x4 - 8x3- 15x2 - 6x - 93

A. Approximate local maxima at -41.059 and -0.241; approximate local minima at -0.573 and 1.984 B. Approximate local maxima at -41.132 and -0.273; approximate local minima at -0.547 and 1.952 C. Approximate local maxima at -41.177 and -0.331; approximate local minima at -0.521 and 1.997 D. Approximate local maxima at -41.106 and -0.213; approximate local minima at -0.519 and 1.924

Mathematics

Find the value of the expression.Let logb 2 = 2.212 and logb 3 = 3.412. Find logb 24.

A. 12.448 B. 27.296 C. 5.624 D. 10.048

Mathematics