If a project is expected to be completed in 68 days with a project variance of 9 days, what is the probability that the project will be completed within 90 days?
A. 85%
B. 90%
C. 95%
D. 100%
D. 100%
You might also like to view...
Country-of-origin perceptions, once formed, are very difficult to change
Indicate whether the statement is true or false
Anna Mia is excited about studying the behavioral science approach in her Principles of Management class. She feels well prepared to study this approach because she has already taken classes in ______, ______, and ______, all of which inform the behavioral science approach.
a. sociology; economics; management science b. economics; philosophy; research c. economics; psychology; sociology d. psychology; sociotechnical theory; economics
Initial conflict between the indigenous peoples in the Americas and Europeans can best be explained by which ethical theory?
a. social group relativism b. cultural relativism c. egoism d. utilitarianism
An example of an item that should be evaluated by a retailer that uses inspection is _____
a. college textbooks b. antique furniture c. color televisions d. file cabinets