Determine the cost to install the metal deck for the floor shown in Problem 7 using a productivity of 2.8 labor hours per square (100 square feet) and an average labor rate of $35.11 per labor hour.

What will be an ideal response?


From Problem 12, the area of the deck is 46.6 sq.

Labor hour = 2.8 lhr per sq × 46.6 sq = 130 lhr

Labor cost = 130 lhr × $35.11/lhr = $4,564

Trades & Technology

You might also like to view...

In a semi-hermetic compressor, _____.

a. the compressor and drive motor share a common housing b. the drive motor is mounted outside of the compressor housing c. the pistons can easily be accessed and serviced in the field d. rotating scroll plates compress the refrigerant progressively

Trades & Technology

When GE crops are grown next to organic farming operations, certain practices that minimize synthetic pesticide drift can also limit GE gene flow, such as spatial separation of fields, staggered planting dates, and planting varieties with different maturity dates and those that are not sexually compatible

Indicate whether the statement is true or false

Trades & Technology

Adapting plants to differing environments is a goal of plant breeders

Indicate whether the statement is true or false

Trades & Technology

Tech A says some rear axle seals are mounted on the inboard side of the axle bearing. Tech B says some are mounted on the outboard side of the axle bearing. who is correct

A. a only B. b only C. both a and b D. neither A nor B

Trades & Technology